Start |
Finish |
Details |
31 May |
1 June |
Installation of new temporary signalling - service unaffected |
14 June |
16 June |
Temporary track alterations - service unaffected |
19 July |
20 July |
New temporary track brought into use |
21 July |
12 Sept |
All trains use Dartford bound platform over single line. |
13 Sept |
15 Sept |
London bound platform reinstated |
25 Oct |
27 Oct |
Reinstatement of normal track layout - service unaffected |
7 Dec |
Removal of tunnelling machine - service unaffected |
Beware: Preparations for the millennium can cause delays/cancellations/diversions to trains at weekends because of engineering work - always check with the operator before travelling
|